Project Inception: March, 2011
Project Revised: June, 2012
Project Completion: September, 2015

Mymensingh Strategic Development Plan (MSDP) Project, 2011-2031

Step 18 :: Regional Growth Center
  • Add Forshore with Road from Ecological Zone    
  • Prepare Map with Road Network and Ecological Zone    
  • Print Map    
  • Sketch on Map for Designing Growth Center     Download Map
  • Scan Map    
  • Georeference Map    
  • Edit Road At Growth Center     Download Map
  • Buffer Road centerline According to Road Type and Lane    
  • Find out the Structures which are affected due to Road widenning    
  • Listing of Affected building By Type & Height    
  • Affected Portion has been Identified from GIS Data    
  • Prepare Database for Road network    
  • Database Varified with Expert opinion    
  • Finalize Road network at growth Centers for MSDP Area